Installation Costs
PREFAFRANCE prefabricated substations offer an optimised solution in terms of cost and installation speed:
- PREFAFRANCE monobloc concrete substation (1 transformer, approx. 3.28 x 2.38 x 3.045 m) → €6,000 to €10,000 excl. VAT (delivered assembled, transport and installation included)
- PREFAFRANCE modular concrete substation (2 transformers) → €10,000 to €15,000 excl. VAT (depending on configuration and chosen options)
- PREFAFRANCE HTA/LV connection (power > 160 kVA) → €14,000 to over €30,000 depending on location, power rating and network complexity
- Ten-year maintenance → €400 to €600 for preventive maintenance of PREFAFRANCE equipment
Installation Timescales
Thanks to factory prefabrication, the timescales offered by PREFAFRANCE are particularly short:
- PREFAFRANCE factory production: 2 to 12 weeks depending on order book and equipment level
- Installation & connection on site: 2 to 5 days (up to 7 days for modular substations)
- Studies and administrative procedures (Enedis/RTE): 2 to 8 weeks
- Civil engineering preparation (slab, earthworks, access): 1 to 3 weeks
Overall duration of a PREFAFRANCE project: 2 weeks to 2–3 months, of which only a few days are for the actual installation.
Installation Steps for a PREFAFRANCE Substation
Studies & authorisations (2 to 8 weeks)
- Definition of client requirements
- Site survey and PREFAFRANCE integration plans
- Approval by Enedis/RTE and obtaining administrative authorisations
Civil engineering preparation (1 to 3 weeks)
- Earthworks, concrete slab, cable ducts, HT/LV reservations
PREFAFRANCE factory production (2 to 12 weeks, in parallel)
- Manufacture of the concrete/steel enclosure
- Integration of equipment (ventilation, doors, rails, transformer, HTA/LV switchboards)
Delivery & installation (1 to 2 days)
- Transport to site
- Placement by crane
- Quality control and PREFAFRANCE acceptance report
Connections & tests (2 to 5 days)
- HTA/LV cable connection
- Installation of earth connections
- Electrical tests and safety checks
Inspection & energisation (1 to 2 days)
- Compliance verification
- Approval by the network operator
- Commissioning of the PREFAFRANCE substation
PREFAFRANCE Summary Table
| PREFAFRANCE prefabricated substation HT/LV | Purchase & installation cost | 10-year maintenance | Production lead time | Installation/connection lead time |
|---|---|---|---|---|
| Monobloc concrete (1 transformer) | €6,000 – €10,000 excl. VAT | ~€400 | 2 to 8 weeks | 2 to 5 days |
| Modular concrete (2 transformers) | €10,000 – €15,000 excl. VAT | ~€600 | 4 to 12 weeks | 2 to 7 days |
| HTA/LV connection >160 kVA | €14,000 – €30,000+ | Included | Subject to complexity | Subject to network |
Conclusion
PREFAFRANCE prefabricated substations enable a significant reduction in lead times and costs compared to traditional construction. Thanks to their modular design and simplified installation, they offer a fast, reliable and secure solution, suited equally to industrial requirements and tertiary infrastructure.